Implementation

Twelve months, three escrowed milestones, fifty families.

The schedule is fixed and the money enforces it: 30% of the General Contractor's compensation is released only against completed, inspected work.

  1. 1

    Month 1 – 3

    Approvals & Capital

    Rezoning, MMF funding approval, and municipal grid permits with the RM of Rosser.

    Rezoning granted
    MMF funding letter
    Water/sewer service agreement
  2. 2

    Month 3 – 5

    Heavy Civil Blitz

    Clearing the 4 acres, excavating the perimeter road and the 8-foot utility trenches.

    4 acres cleared
    Perimeter road sub-base
    8-ft trench corridor open
  3. 3

    Month 5 – 6

    Gravel & Shell Delivery

    Front lot graveling, the 20-stall parking lot, and delivery of the bulk shed shells.

    20-stall lot complete
    50 shells on site
    Master meter live
  4. 4

    Month 6 – 10

    Métis Apprentice Assembly Line

    On-site framing, spray-foam winterization, and hydronic PEX floor layouts by the Métis labour and apprentice loop.

    50 units framed
    50 units foamed
    PEX floors pressure-tested
  5. 5

    Month 9 – 11

    Hub, Solar & Boiler

    Central Communal Hub construction, solar array installation, and boiler activation.

    Hub lockup
    Array energized
    Hydronic loop commissioned
  6. 6

    Month 11 – 12

    Occupancy & Move-In

    RM of Rosser master occupancy inspection, shuttle van launch, and 50-family move-in.

    Occupancy permit
    Shuttle in service
    50 families housed

General Contractor — Project Management Services Agreement

A flat annual fee rather than a percentage of construction, so administrative cost does not scale with the capital budget. Funded through CMHC soft-cost grants.

Total annual fee

$150,000

Flat Project Management Services Agreement, 12-month term.

Base salary — 70%

$105,000

Paid bi-weekly for day-to-day workforce management.

Milestone bonuses — 30%

$45,000

Held in project escrow, released only on verified completion.

Month 5

$15,000

Bonus 1

Rosser municipal water/sewer grid connection complete

Month 10

$15,000

Bonus 2

Structural lockup, framing, and spray-foam of all 50 units

Month 12

$15,000

Bonus 3

Final master occupancy sign-off from RM of Rosser inspectors

Procurement

Flat-packed kits, not fifty wide loads.

Two ways to prefabricate fifty homes: buy them finished and truck each one down the highway as an oversize load, or buy stamped panel kits nearby and stand them up on site. Modelled against Rosser conditions, the kit pathway is cheaper to move, gentler on the clay, and keeps the trade hours in the community.

FactorPanel kit — assembled on siteFinished module — delivered whole
Highway loads for 50 homes6 – 8 legal-width flatbed loads, panels stacked flat50 individual oversize loads, 12 – 14 ft wide
Permits & escortsNone — standard legal width50 Manitoba Infrastructure oversize permits plus pilot escorts
Modelled freight cost$12,000 – $18,000 total (≈ $250 – $360 per home)$150,000 – $225,000 total (≈ $3,000 – $4,500 per home)
Impact on Rosser clayTelehandler off the gravel entrance lot; light ground pressureMobile crane or float trailer on soft gumbo; rut and sub-base risk
Modelled shell cost$16,000 – $19,500 (floor cassette, 2×6 walls, engineered trusses)$65,000 – $85,000 factory-finished
On-site Métis trade hours4,000 – 6,000 hours across framing, foam, PEX and finishingUnder 500 hours — rigging and service tie-ins only
Wage subsidy captureQualifies for ISET and LRCC apprenticeship wage supportLittle to no on-site apprentice capture
Inspection pathwayP.Eng.-stamped shop drawings plus RM of Rosser Part 9 batch reviewCSA A277 plant label; site permit covers siting and services only

Cost and load figures are planning estimates for comparison only, pending written supplier quotations.

Preferred pathway

Winnipeg & Headingley panel corridor

Wall panel, floor cassette and engineered truss plants sit within roughly 20 km of the site along the Perimeter Highway. Short legal-width hauls, just-in-time delivery, no pilot vehicles.

Benchmark only

Southern Manitoba volumetric plants

Winkler and Steinbach CSA A277 module builders deliver excellent factory quality, but unit price and 125 km of oversize hauling put the model above the $30,000 per-unit capital cap.

Recommended

Hybrid dry-shell model

Buy the structural kit locally, lock up each home weather-tight in 24 – 48 hours on timber skids, then complete foam, hydronics and finishes indoors with Métis apprentice crews.

Four crews, twelve days, one finished home.

The same four crews move down the rows in sequence, so a crew repeats one task fifty times instead of learning twelve.

Crew 1

Skids & floor cassette

Days 1 – 2 per cluster

  • Pressure-treated timber skids levelled on 150 mm compacted Class A gravel
  • Pre-insulated floor cassettes set, squared and strapped down
  • Tongue-and-groove subfloor glued and fastened
Crew 2

Panel stand & lockup

Day 3 per unit

  • Pre-sheathed 2×6 wall panels stood and fastened
  • Engineered trusses set, roof sheathed and metal roofing fastened
  • Windows and exterior doors hung — weather-tight within 24 – 48 hours
Crew 3

Envelope & hydronics

Days 4 – 6 per unit

  • 3" closed-cell spray foam to walls and roofline (MBC 9.25)
  • Subfloor PEX loops stapled with heat-transfer plates, pressure-tested
  • Mini HRV set and ducted for balanced continuous ventilation
Crew 4

Rough-in, drywall & finishes

Days 7 – 12 per unit

  • PEX tie-in to the buried district loop; electrical harness to the sub-panel
  • Drywall, vinyl plank flooring and pre-built cabinetry
  • Alarms commissioned and unit readied for occupancy inspection

The Métis labour loop

100% on-site Métis labour

Framing, spray foam, PEX layout, and finishing are performed by Red River Métis crews under the GC's management.

Apprentice training loop

The assembly line runs as a training environment: fifty identical units means fifty repetitions of every trade task, logged toward apprenticeship hours.

Wages stay in the community

Construction payroll circulates inside the same community the housing serves, and crews emerge with transferable certification.