Grant stacking data room

Clear the capital cost upfront, so residents never pay interest.

As a certified Métis-owned corporation, nott Technologies Inc. can stack Indigenous-governed, federal, and institutional capital pools to fully fund construction before the first family moves in.

Hard-cost target — 50 units × $30,000

$1,500,000

Stacked from selected sources

$1,650,000

Remaining gap

$0

100% of hard costs covered. Soft costs — including the $150,000 GC agreement — are funded separately through CMHC and do not draw on the construction stack.

Capital pools

Uncheck a source to test the stack's resilience if a submission is unsuccessful.

Primary
URNIHS

Urban, Rural and Northern Indigenous Housing Strategy

Administered for Red River Métis citizens through the MMF

Raw materials: shells, spray foam, PEX, XPS skirting, HRVs.

Coverage
Capital stream — Indigenous-governed allocation
Modelled contribution
$600,000

Eligibility requirements

  • Indigenous-led, Indigenous-governed housing proponent
  • Units dedicated to Indigenous households in core housing need
  • Long-term affordability covenant on the land trust
Primary
RHII

Regional Homebuilding Innovation Initiative

Federal — high-volume innovation funding

Up to 50% of construction cost for modular and rapid-assembly delivery.

Coverage
Up to 50% of construction cost
Modelled contribution
$525,000

Eligibility requirements

  • Demonstrated modular or factory-built assembly method
  • Measurable cost-per-unit and schedule reduction versus site-built
  • Workforce development component
Stackable
Reaching Home

Reaching Home — Indigenous Homelessness Stream

Federal — supportive housing infrastructure

Fully funds the Central Communal Hub and the 15-passenger shuttle van.

Coverage
Hub + transit capital
Modelled contribution
$275,000

Eligibility requirements

  • Indigenous-specific service delivery
  • Supportive / wraparound programming plan
  • Community entity endorsement
Soft cost
CMHC

CMHC Soft-Cost & Seed Funding

Canada Mortgage and Housing Corporation

Covers the $150,000/yr flat GC Project Management Services Agreement, design, and permitting.

Coverage
Soft costs and pre-development
Modelled contribution
$150,000

Eligibility requirements

  • Site control or option agreement
  • Preliminary design and cost estimate
  • Evidence of municipal support
Stackable
LRCC

Louis Riel Capital Corporation

MMF-affiliated Métis financial institution

Bridge financing between grant tranches; Métis business capital for nott Technologies Inc.

Coverage
Bridge / gap
Modelled contribution
$100,000

Eligibility requirements

  • Red River Métis citizen-owned business
  • Viable repayment or grant-takeout schedule
Stackable
Net Billing

Manitoba Hydro Commercial Net Billing

Manitoba Hydro

Summer overproduction from the Hub array banks credits that offset overnight winter hydronic pumping load.

Coverage
Operating offset
Modelled contribution
Operating offset

Eligibility requirements

  • Interconnection agreement + CSA C22.1 Section 64 compliant install
  • Commercial-class metering at the master node
  • Array sized to on-site annual consumption

Submission package checklist

Site control

  • 4-acre parcel option or purchase agreement
  • RM of Rosser rezoning application
  • Municipal servicing agreement

Design & compliance

  • CSA A277 shell certification
  • Stamped site servicing drawings
  • MBC 9.36 energy compliance path

Financial

  • $1.5M hard-cost estimate
  • 10-year operating pro forma at $600/unit
  • Métis Land Trust title structure

Governance

  • MMF endorsement letter
  • Land Trust constituting documents
  • Resident selection and allocation policy

Workforce

  • Métis apprenticeship plan
  • GC Project Management Services Agreement
  • Milestone escrow instrument

Energy

  • Manitoba Hydro interconnection application
  • Array production model
  • Boiler fuel supply agreement

Modelled contributions are planning allocations used to test the stack, not committed funding. Each source carries its own application window, reporting regime, and eligibility determination.